Upgrade
Upgrading is intended for deployers with development experience and is an atomic process you orchestrate: the "database migration SQL → backend → frontend" replacement must be completed within the same maintenance window. Any intermediate state mixing old and new artifacts can break things — for example, API changes in a new backend can break the old frontend, and once a migration that renames tables has been executed, queries from the old backend fail immediately.
1. Determine Current and Target Versions
Your currently deployed version defines the migration starting point: every incremental script (
NNN_*.sql) numbered no greater than the current version has already been appliedThe migrations to run are the incremental scripts added between the two versions:
bashgit diff --name-only <current>..<target> -- server/db_migrationMigration scripts live in server/db_migration; see that directory's README for naming conventions and how to run them
2. Prepare
Back up the database — for disaster recovery (rebuilding if the upgrade fails or data is corrupted):
bashpg_dump -h <host> -U <user> -d aideepin -F c -f aideepin_backup_$(date +%Y%m%d).dumpFor Docker deployments, also update
IMAGE_VERSIONin.env: images are tagged with this value, so incrementing it per release keeps previous images availableFor bare-metal deployments, make sure JDK 21+ is installed: the backend is compiled for Java 21 from this release on, so both building and running require JDK 21+ and an older JDK cannot start the new JAR (Docker images bundle JRE 21 and are not affected)
3. Perform the Upgrade
Complete the steps in order within a maintenance window; the service is unavailable during it:
- Stop the services. All-in-one: run
docker compose downin the rootdocker/directory; per-service Docker: in each sub-project'sdocker/directory; bare-metal: stop the backend process - Run database migrations: starting from the number that corresponds to your current version, execute all incremental migration scripts in numeric order (see the db_migration README)
- Check out the target version:
git checkout <tag or commit> - Rebuild and start:
- All-in-one:
docker compose up -d --buildin the rootdocker/directory - Per-service Docker:
docker compose up -d --buildin each sub-project'sdocker/directory - Bare-metal:
mvn clean package -Dmaven.test.skip=true, replace the JAR, and start it (see Bare-metal deployment)
- All-in-one:
- Verify: sign in to the user web and admin web, and check that core features (chat, knowledge base, workflow) work
4. About Rollback
Database rollback is not supported: migration scripts are forward-only — there are no rollback scripts, applied migrations cannot be undone, and the schema does not revert when the backend does. Any combination of "old backend/frontend + migrated database" is unsupported — even additive-looking migrations may modify data the old version depends on. Therefore:
- Rehearse the full upgrade in a test environment before touching production
- The pre-upgrade database backup is for disaster recovery (rebuilding the database, recovering data), not for version rollback; restoring it discards everything produced after the upgrade and is an at-your-own-risk manual operation